Program Updates

Recent Annual Expenditures on Resurfacing

Year Amount
2019 $4,724,000 (77% Increase Over 2018)
 2018  $2,669,000
2017 $2,504,000
2016 $1,553,000
2015 $1,086,000
2014 $834,000
2013 $946,000
2012 $1,042,000
2011 $1,216,000
2010 $761,000
2009 $1,330,000

The amount does not include outside funding sources.

Recent History of Improvements to Canton's Paving Program

  • 2019
    • 3 Keys
      • Coordination
      • Life Cycle Cost Analysis
      • Preventive Maintenance
    • New Pavement Management Approach
  • 2018
    • Begin to use increased funds from Issue Number 13 Tax Issue
  • 2017
    • Started using cement base stabilization
  • 2015
    • Started using Chip Seal