Board of Control Agenda


AGENDA

BOARD OF CONTROL

 

Tuesday, January 21, 2020

Mayor’s Conference Room: 8th Floor City Hall

9:00 AM


Ordinance 2/2020

1.  Enter into a one-year professional services contract with AultCare Insurance Company for a pharmacy prescription plan for City employees at a rate of $90.15 per employee per month.


Ordinance 22/2019

2.  Enter into Change Order No. 2 with Wenger Excavating, Inc. for the 33rd St. Area Water Main Replacement Project due to a time extension request for paving to be done in the spring, resulting in a new final completion date of May 15, 2020.


Ordinances 29/2019 & 30/2019

3.  Enter into Change Order No. 2 & Final with Arcadis U.S., Inc. for the Perry/Tuscarawas/Woodlawn Phase I and II Water Main Project for a cost reduction in the amount of $312,576.12, resulting in a new contract amount of $49,394.11.  This is due to other projects in this area being planned by ODOT and the Stark County Engineer which will be combined with City projects.